Guide
Air compressor service intervals: hours, calendar and the legal bit
Updated
Two clocks run on a compressor house, often confused. One is the manufacturer's service schedule; the other, the statutory examination under your written scheme. Neither sets the other.
Clock one: the manufacturer's schedule
Routine servicing intervals are set by the machine's manufacturer, normally in running hours, sometimes with a calendar backstop for machines that run little.
The handbook is the authority for your model. Hours vary between makes, oil types and duty cycles. A continuously running machine reaches its major service several times while a lightly loaded one reaches it once.
- Read hours, not months. Fit an hours meter reading into your planning, and set the calendar visit around it rather than the other way round.
- Oil type changes the interval. Mineral, semi-synthetic and full-synthetic lubricants carry different service lives, and using a longer-life oil is a legitimate way to stretch an interval if the manufacturer allows it.
- Ambient conditions shorten it. Dust, heat and poor ventilation load the coolers and the intake filter. A foundry compressor house is not a clean assembly hall.
- Air treatment runs on its own schedule. Filter elements, drains and desiccant charges are not tied to the compressor's hours.
Clock two: the statutory examination
Compressed air above 0.5 bar above atmospheric pressure is a relevant fluid. So the installation is a pressure system under the Pressure Systems Safety Regulations 2000 (HSE). A written scheme of examination must be in place, and an examination done, before qualifying equipment is used. Thereafter the system must be examined in accordance with that scheme.
There is no statutory interval to quote: PSSR names no number of months or years for compressed air. Your written scheme sets the frequency, drawn up or certified by a competent person for your system. Anyone saying the law requires every two or four years is describing a scheme they have seen. See the written scheme guide.
How the two clocks work together in practice
- Put both on one plan. Manufacturer service dates by hours, examination dates by scheme, on the same calendar, so nothing is missed and visits can be combined where the provider can do both.
- Keep the records. PSSR includes duties on maintenance and the keeping of records (regulations 12 and 14), and a maintenance log is also a PUWER expectation for work equipment generally.
- Review the scheme when the plant changes. New receiver, re-piped ring main, changed duty: the competent person should confirm the scheme still fits.